We’ll be posting the latest news for Eyot House, Bermondsey customers here, so please bookmark this page to stay up to date on the work we’re doing to keep everyone safe.
Latest update - 8 December 2023
Amber Construction has completed measuring the spandrel panels and left the site. The scaffold has also been taken down.
We’ll share another update with next steps once this has been confirmed. However, work is still expected the begin in in early 2024.
Project Summary
Our engineer’s report has found that 81 spandrel panels need to be replaced so that an EWS1 with a favourable rating (B1) can be issued.
We expect the spandrel replacement work to start in early 2024.
Estimated programme dates:
Action |
Date |
Lead time for panels (8 weeks) |
November 2023 to |
Mobilisation and site set up |
Week commencing |
Replacement work to start |
Week commencing |
Replacements expected to be completed |
March 2024 |
Decant site & EWS1 form issued |
March 2024 |
Clarification on costs for leaseholders
Although we’ve made applications to the Government's Building Safety Fund, and to provide assurance to leaseholders, we can confirm that in respect of Eyot House, where Hyde is the current landlord, Hyde was the developer or was associated with the developer for the purposes of the Building Safety Act 2022. By ‘developer’ we mean that Hyde was the party that appointed Rok Group as the Principal Contractor who was responsible for designing and constructing the building.
The fact that Hyde was the developer means that we can’t pass on charges to leaseholders for the costs of remediation works to “relevant defects”. The works identified in this instance, are classed as “relevant defects”, as outlined in the Building Safety Act.
We can also confirm that the replacement of panels at Eyot will be carried out whether or not our applications are successful.
Building Safety Fund
Our applications (for blocks A and B, see below) have gone through the technical eligibility criteria for the replacement of the spandrel panels, and it has been confirmed that they meet the legal criteria for funding. The applications will now move to the next stage of the process, which is cost review. Once we agreed the cost with our contractor, we’ll provide them to fund processors. The application status is currently “Eligibility Confirmed”. As soon as we hear from DLUHC on the next step, we’ll update you.
Block A is the Marine Street postal address, flats 1-52, and Block B the Sun Passage address, flats 53-114.
The Government is publishing updates on how Building Safety Fund applications are progressing in the third week of each month on the Building Safety Fund Leaseholder and Resident Service website pages.
Customers must use a code unique to their building to access the service. We’ve shared this code with customers, which and can be shared again via email [email protected].
If you have any queries about the work, please email us at [email protected].
Next Resident Project meeting
The next meeting will be held on Wednesday 17 January 2024 at 1pm via Zoom.
Meeting invitations will be sent out ahead of the meeting.
Download a copy of your building’s fire risk assessment
You can download a copy of the latest fire risk assessments for 1-52 Eyot House (PDF, 2MB) and 53-114 Eyot House (PDF, 2MB). Any actions in the fire risk assessment will be completed by the due date stated.
Get in touch
If you have any questions that aren’t related to the remediation work, please email us at [email protected]