Bolanachi Building - building safety

We’ll be posting the latest news for Bolanachi Building, Bermondsey customers here, so please bookmark this page to stay up-to-date on the work we’re doing to keep everyone safe.

Latest update - 23 May 2022

Kier is removing the combustible timber at Bolanachi in the internal and external courtyard. The external courtyard has been completed and all scaffolding has been removed. The timber replacement in the internal atrium has completed and is currently being signed off and snagged by Kier.

The scaffold strike started the week commencing Monday 9 May. All timber replacement works are due to be completed by the end of May.

Building Safety Fund application

We’re still waiting for a decision on the outcome of our Building Safety Fund application. We continue to meet with the Department for Levelling Up, Housing and Communities, but decisions continue to be delayed due to the volume of applications. We’re sorry, but this means we still can’t tell you when we’ll find out if we’ve been successful and, if we are, how much funding we’ll receive. We’ll update you as soon as we know more.

The Building Safety Fund Leaseholder and Resident Service

Government is publishing updates on how Building Safety Fund applications are progressing in the third week of each month on Building Safety Fund Leaseholder and Resident Service website pages.

Customers must use a code unique to their building to access the service. We’ve shared this code with customers and can share it again via email, on request.

Answering your questions

Please check the Bolanachi Q&A document (PDF, 555KB), which has the answers to many of the questions being raised by customers on the building safety issues.

Project update meeting: Wednesday 1 June 2022, 4pm

The next project meeting will be held on Wednesday 1 June at 4pm. We’ll use the same Zoom link as for previous meetings. Reminders will be sent out in advance.

Project: What we're doing

Our contractor Kier will be removing and replacing the timber in the courtyard and the walkways in the atrium with aluminium with a timber effect finish. The team will be following coronavirus guidelines, including social distancing.

Martin Arnold is the Designer and Employer’s Agent for the project.

Contacts

Resident Liaison Officer: Adam Buckner, 07594 519835 or email adam.buckner@kier.co.uk

Site Manager: Duncan Ferreira, 07970 909096 or email duncan.ferreira@kier.co.uk

What to do in the event of a fire

The evacuation strategy is ‘simultaneous evacuation’. This means that if you're alerted to a fire, you must evacuate the building immediately.

Find out what to do in the event of a fire.

EWS1 forms

A fire engineer will be involved throughout the project to ensure an EWS1 form will be issued about six to eight weeks after work is completed.

If you want to find out more about EWS1 forms, please visit our EWS pages, where you can find an overview of the issues surrounding external wall surveys and the answers to the most frequently asked questions.

Download a copy of your building’s fire risk assessment

You can download a copy of the latest fire risk assessment for Bolanachi Building (PDF, 9.9MB). Any actions in the fire risk assessment will be completed by the due date stated.

Get in touch

If you have any questions relating to the project, please email us at residentfiresafety@hyde-housing.co.uk