Provisional external wall system survey programme 2021-23

We expect to appoint our new external wall system (EWS) survey providers in July 2021, following the conclusion of our consultation with customers. In the meantime, we wanted to share our provisional EWS programme for the next two years. This programme will be finalised once the providers have been appointed formally.

We’ll continue to take a risk-based approach to EWS surveys, which means we will focus first on our tallest buildings presenting the most risk, ie those with ‘significant’ cladding (more than 40% of the outside walls, according to Government guidelines), before moving onto lower risk buildings.

It’s important to remember that we need to carry out an EWS survey before an EWS1 form can be completed. The timescales in the tables below are based on completing an EWS survey. Following the survey, we’ll take two courses of action:

  • If the EWS survey suggests the building will be given a satisfactory EWS1 rating, we’ll instruct our provider to carry one out straight away
  • If the EWS survey suggests the building won’t be given a satisfactory EWS1 rating, then we’ll need to carry out remedial works before we instruct our provider to complete an EWS1 form. This is because the cost of completing the EWS1 form is on top of the EWS survey and we don’t want anyone to incur unnecessary costs.

We’ll be in touch with customers before, during and after the EWS surveys to keep them updated on progress.

Finding your building in the table

We’ve listed buildings that are included in the EWS survey programme, in the table below. Buildings are listed by postcode and then in alphabetical order. Once you’ve found your building, you’ll find its EWS survey status (details below). Alternatively, we’ve also provided a list of buildings in separate tables under each of heading (PDF, 148KB) that you can download here.

Buildings of six storeys or more – with cladding

We’ll be carrying out EWS surveys on a number of buildings of six storeys or more, with cladding, between March 2022 and March 2023.

Buildings of six storeys or more – without ‘significant’ cladding

We’ll carry out visual inspections of buildings of six storeys of more without ‘significant’ cladding (ie with less than 40% cladding) by March 2022 and provide a report that will demonstrate to lenders that an EWS1 form is not needed.

Buildings that have already had an external wall inspection, or where work is underway

A number of our buildings have already been investigated and we’ll be updating customers regularly, primarily on the building safety section of our website.

Buildings of six storeys or more, where Hyde isn’t responsible for the external walls

We have homes in some buildings of six storeys or more where we’re not responsible for the external walls, so we cannot instruct our EWS surveyors to complete a report. We’ll continue to work with building owners and managers to ensure they provide us with an EWS1 form that we can share with you

Buildings below six storeys

If your building isn’t listed here, then it’s likely that it has fewer than six storeys and is not currently in the EWS programme.

The Fire Safety Act 2021, that came into force in April 2021, requires all buildings of two or more ‘premises’ (ie homes or commercial units), regardless of height to have an EWS survey, as part of their overall fire risk assessment. However, according to guidance from the Royal Institute of Chartered Surveyors, only those buildings below six storeys meeting certain criterial require an EWS1 form.

We’ll be working with our EWS surveyors to put together a plan for EWS surveys for buildings below six storeys over the coming months and aim to share this with customers by March 2022. However, this means we may not start carrying out surveys on these buildings until April 2023, once we have finished surveying our taller buildings.


Postcode

Building

EWS survey status

BN1

Embankment House, BN1

Already been investigated – check the building safety page for this build

BN1

Temple House, BN1

Already been investigated – check the building safety page for this building

BN1

The Barrows, BN1

EWS survey to be completed between March 2022 and April 2023

BN2

Ebenezer Apartments 1-24, BN2

EWS survey to be completed by March 2022

BN2

Ebenezer Apartments 25-49, BN2

EWS survey to be completed by March 2022

BN2

Viaduct Lofts, BN2

EWS survey to be completed by March 2022

BR1

Henry House, BR1

Hyde isn’t responsible for the external wall – we’re working with the building owner or manager to obtain an EWS1 form

BR1

William House, BR1

Hyde isn’t responsible for the external wall – we’re working with the building owner or manager to obtain an EWS1 form

BR14

Treversh Court, BR14

Visual inspection of EWS by March 2022

BR3

County House, BR3

EWS survey to be completed between March 2022 and April 2023

CR0

Gary Court, CR0

Already been investigated – check the building safety page for this building

CR0

Woodall Court CR0

Hyde isn’t responsible for the external wall – we’re working with the building owner or manager to obtain an EWS1 form

CR0

453-461 Purley Way and 4-80 Propeller Crescent, CR0

Already been investigated – check the building safety page for this building

DA9

Bessborough House, DA9

Hyde isn’t responsible for the external wall – we’re working with the building owner or manager to obtain an EWS1 form

DA9

Clarinda House, DA9

Hyde isn’t responsible for the external wall – we’re working with the building owner or manager to obtain an EWS1 form

HA1

Pearson Apartments, HA1

Hyde isn’t responsible for the external wall – we’re working with the building owner or manager to obtain an EWS1 form

HA9

Ada Lewis House, HA9

EWS survey to be completed by March 2022

HA9

Wealdstone Court, HA9

Already been investigated – check the building safety page for this building

ME1

1 Limehouse Wharf, ME1

Hyde isn’t responsible for the external wall – we’re working with the building owner or manager to obtain an EWS1 form

ME14

Shipley Court, ME14

Visual inspection of EWS by March 2022

ME7

South Shore, ME7

Hyde isn’t responsible for the external wall – we’re working with the building owner or manager to obtain an EWS1 form

N1

1 Ann Street; and 6 and 8 Packington Square, N1

Already been investigated – check the building safety page for this building

N1

3 Ann Street, N1

Already been investigated – check the building safety page for this building

N1

4 Ann Street, N1

Already been investigated – check the building safety page for this building

N1

6, 6a and 8 Ann Street, N1

Already been investigated – check the building safety page for this building

N1

74 Arlington Avenue, N1

Already been investigated – check the building safety page for this building

N1

87 Arlington Avenue 87, flats 1-12, N1

Already been investigated – check the building safety page for this building

N1

89 Arlington Avenue 89, flats 1-22 N1

Already been investigated – check the building safety page for this building

N1

11-16 Canalside Square,N1

Already been investigated – check the building safety page for this building

N1

17 Canalside Square, N1

Already been investigated – check the building safety page for this building

N1

1-7a Canalside Square, N1

Already been investigated – check the building safety page for this building

N1

8 Canalside Square, N1

Already been investigated – check the building safety page for this building

N1

9 and 10 Canalside Square, N1

Already been investigated – check the building safety page for this building

N1

18 Canalside Square N1

Already been investigated – check the building safety page for this building

N1

79 Dame Street, N1

Already been investigated – check the building safety page for this building

N1

1 Packington Square, N1

Already been investigated – check the building safety page for this building

N1

2-5 Packington Square, N1

Already been investigated – check the building safety page for this building

N1

10 Packington Square, N1

Already been investigated – check the building safety page for this building

N1

12 Packington Square, N1

Already been investigated – check the building safety page for this building

N1

55 St Paul Street, N1

Already been investigated – check the building safety page for this building

N1

8-24 Prebend Street and 51 Packington Street, N1

Already been investigated – check the building safety page for this building

N7

Tealby Court, N7

Visual inspection of EWS by March 2022

NW1

57 Hillside, NW1

Visual inspection of EWS by March 2022

NW10

2 Hillside, NW10

EWS survey to be completed by March 2022

NW10

8 Hillside, NW10

EWS survey to be completed by March 2022

NW10

75-115 Shakespeare Road, NW10

EWS survey to be completed between March 2022 and April 2023

NW10

Allegro House, NW10

EWS survey to be completed by March 2022

NW10

Camellia Apartments, NW10

EWS survey to be completed between March 2022 and April 2023

NW6

9 Willesden Lane, NW6

EWS survey to be completed between March 2022 and April 2023

PO12

Blake Court, PO12

Already been investigated – check the building safety page for this building

PO12

Garland Court, PO12

Already been investigated – check the building safety page for this building

PO12

Hammond Court, PO12

Already been investigated – check the building safety page for this building

PO12

Harbour Tower, PO12

Already been investigated – check the building safety page for this building

PO12

Seaward Tower, PO12

Already been investigated – check the building safety page for this building

PO5

Sir Robert Peel House, PO5

EWS survey to be completed by March 2022

RH15

Wynnstay, RH15

EWS survey to be completed between March 2022 and April 2023

SE1

Artesian House, SE1

Already been investigated – check the building safety page for this building

SE1

8 Melior Street, SE1

Hyde isn’t responsible for the external wall – we’re working with the building owner or manager to obtain an EWS1 form

SE1

251 Southwark Bridge Road, SE1

Hyde isn’t responsible for the external wall – we’re working with the building owner or manager to obtain an EWS1 form

SE10

1-11 Norway Street, including Hargood House, SE10

Hyde isn’t responsible for the external wall – we’re working with the building owner or manager to obtain an EWS1 form

SE10

Dowells Street, SE10

Hyde isn’t responsible for the external wall – we’re working with the building owner or manager to obtain an EWS1 form

SE10

Freemantle House, SE10

Hyde isn’t responsible for the external wall – we’re working with the building owner or manager to obtain an EWS1 form

SE10

Gladstone House, SE10

Hyde isn’t responsible for the external wall – we’re working with the building owner or manager to obtain an EWS1 form

SE14

Avonley Road, SE14

EWS survey to be completed by March 2022

SE14

Empire Heights, SE14

Hyde isn’t responsible for the external wall – we’re working with the building owner or manager to obtain an EWS1 form

SE14

Wardalls Grove, SE14

EWS survey to be completed by March 2022

SE15

Gately Court, SE15

EWS survey to be completed by March 2022

SE15

2 Woods Road, SE15

Hyde isn’t responsible for the external wall – we’re working with the building owner or manager to obtain an EWS1 form

SE16

Bolanachi Building, Bermondsey Spa, SE16

Already been investigated – check the building safety page for this building

SE16

Calico Court, SE16

EWS survey to be completed between March 2022 and April 2023

SE16

Davoll Court, SE16

Already been investigated – check the building safety page for this building

SE16

Eyot House, SE16

Already been investigated – check the building safety page for this building

SE16

Hicks House, SE16

Already been investigated – check the building safety page for this building

SE16

Kimmins Court, SE16

Visual inspection of EWS by March 2022

SE16

Parker Building, SE16

Already been investigated – check the building safety page for this building

SE16

Pitman Building SE16

EWS survey to be completed between March 2022 and April 2023

SE16

Porter Building, SE16

Visual inspection of EWS by March 2022

SE16

Prospect House, SE16

Already been investigated – check the building safety page for this building

SE18

Argyll Road, flats 271,289,291,312,313,315, SE18

Hyde isn’t responsible for the external wall – we’re working with the building owner or manager to obtain an EWS1 form

SE18

2-9 Artillery Place, incl. Brixham Building, SE18

EWS survey to be completed between March 2022 and April 2023

SE19

55 Church Road, SE19

Visual inspection of EWS by March 2022

SE19

57 Church Road, , SE19

Visual inspection of EWS by March 2022

SE8

Longshore, 1-15, SE8

EWS survey to be completed between March 2022 and April 2023

SE8

Longshore, 16-27, SE8

EWS survey to be completed between March 2022 and April 2023

SE8

Longshore, 28-42, SE8

EWS survey to be completed between March 2022 and April 2023

SE8

Mereton Mansions, SE8

Visual inspection of EWS by March 2022

SE8

Millard Road, 1-21, SE8

Already been investigated – check the building safety page for this building

SE8

Millard Road, 22-39, SE8

Already been investigated – check the building safety page for this building

SE8

Millard Road, 70-87, SE8

Already been investigated – check the building safety page for this building

SE8

Millard Road, 88-108, SE8

Already been investigated – check the building safety page for this building

SW4

Edrich House, SW4

Visual inspection of EWS by March 2022

SW4

Gover Court, SW4

Visual inspection of EWS by March 2022

SW4

Hayward Court, SW4

Visual inspection of EWS by March 2022

SW4

Holmes Court, SW4

Visual inspection of EWS by March 2022

SW4

Jephson Court, SW4

Visual inspection of EWS by March 2022

SW4

Knox Court, SW4

Visual inspection of EWS by March 2022

SW4

Laker Court, SW4

EWS survey to be completed between March 2022 and April 2023

SW4

Sandham Court, SW4

Visual inspection of EWS by March 2022

SW4

Squires Court, SW4

Visual inspection of EWS by March 2022

SW4

Strudwick Court, SW4

Visual inspection of EWS by March 2022

SW4

Whittaker Court, SW4

Visual inspection of EWS by March 2022

SW8

Benville House, SW8

Visual inspection of EWS by March 2022

SW9

Arden House, SW9

Visual inspection of EWS by March 2022

SW9

Beckett House, SW9

Visual inspection of EWS by March 2022

SW9

Birrell House, SW9

EWS survey to be completed between March 2022 and April 2023

SW9

Cassell House, SW9

Visual inspection of EWS by March 2022

SW9

Morant House, SW9

Visual inspection of EWS by March 2022

SW9

Pinter House, SW9

Visual inspection of EWS by March 2022


Return to top